Technical review · PLAN-X
Draft correspondence, review requests and modeling memorandum
Draft correspondence, review requests and modeling memorandum. Irregular dates, placeholders and blank response fields remain visible. Model predictions and proposed limits are not measured discharge results or final approval.
Source pages 269–274, 290–291 · 8 source pages · Selected records
About this selection
These pages come from the 688-page TCEQ production for the Southwest wastewater plant. Page labels below identify the original production; selected source images and existing redactions are preserved.
Reading context and source notes
The draft letter retains the irregular date on source 269 and Date, 2025 placeholder on source 270. Sources 271–274 preserve the review-request context and blank response fields; blanks do not establish that no response exists elsewhere.
The May 14, 2025 modeling memorandum supersedes a November 13, 2023 memorandum. Model predictions and proposed limits are not measurements of actual discharge or a final approval.
Permit-writer comments distinguish denied reductions from those proposed for winter ammonia and total nitrogen. 2018 conductivity three/week, 2026 one/week. Direct contacts are masked.
Related records
The application, models, sampling-waiver correspondence, maps and photographs explain what was submitted and reviewed. Compare them with the issued terms and separately dated monitoring records. An application-sampling waiver is not a waiver of routine permit monitoring; models, applicant estimates and source captions do not establish measured performance or current conditions.