Application and supporting records · PLAN-K
Technical application
Technical application report in agency production order, with its tables, footnotes and pagination gaps. Treatment and sampling statements remain applicant-supplied; differing sample windows and one-sample/two-sample notes remain unresolved. These are not independent compliance findings.
Source pages 413–449 · 37 source pages · Selected records
About this selection
These pages come from the 688-page TCEQ production for the Southwest wastewater plant. Page labels below identify the original production; selected source images and existing redactions are preserved.
Reading context and source notes
All 37 consecutive source pages (413-449) are retained in agency order. This is the produced technical-report sequence, not a claim that all 75 printed template pages are present. Printed page 42 appears between 28 and 29; other pagination gaps remain.
The signature image on 429 is masked. It overlaps the start of a regulatory-citation line; that short printed segment is masked with it. The citation is also printed elsewhere on the same page. No replacement source text is inserted.
Treatment, flow, impoundment and receiving-water statements remain applicant assertions. All definitions, footnotes, conditional stop instructions, blank sections and tables are preserved.
Source 429 states a January 17-February 8, 2023 sampling range; table dates on 430 and 433 extend beyond it. Sources 431 and 432 retain conflicting one-sample/two-sample notes. PLAN-B grants two metals samples and one organics sample; the conflicting note is not repaired.
Units, less-than signs, MAL columns and margin annotations remain. MAL values are not substituted for permit limits, and application sampling is not routine permit monitoring or an independent compliance finding.
PLAN-C maps, PLAN-D chemical/laboratory summaries and PLAN-B waiver provide related context. The January 2022 receiving-water observation notes prior-day rainfall; no dry-weather or present-condition conclusion.
Jump to a source page
Related records
The application, models, sampling-waiver correspondence, maps and photographs explain what was submitted and reviewed. Compare them with the issued terms and separately dated monitoring records. An application-sampling waiver is not a waiver of routine permit monitoring; models, applicant estimates and source captions do not establish measured performance or current conditions.